I would like to use a Project Template to start a Project and have all dates be based upon a Project Completion/Due Date.
We have a recurring Project Plan that we use which has milestones with completion dates that are calculated to be completed so many weeks before the actual seminar event date. Other milestones are calculated so many weeks after the actual seminar event date.
I would like to have my To Do's be calculated with a particular milestone date in mind.
In MS Project I can have my events with lead and lag times related to particular events/milestones. I would like to be able to do the same thing with Freedcamp.
Hi,
Done. Documentation is updated https://freedcamp.com/Freedcamp_LxR/Freedcamp_Devel_yOf/wiki/wiki_public/view/Ogaab
- please see animated GIF where I show how to switch to plan backward.
Cheers,
Igor
-
Igor commented
We will redo templates in a way described in a comment here - https://freedcamp.uservoice.com/forums/126945-suggestions-for-features/suggestions/4405544-project-template-use-existing-project-as-templat.
We will provide you an option to select start date or end date as it makes sense and recalculate all other due dates accordingly forwards (if start date was specified) or backwards (if end date was pecified).