Gantt chart - dependent tasks move forward automatically
Its would help scheduling that if a project or all projects that are linked in time and dependent of one anothers completion that if a single task has to be scheduled forward in time or took longer to complete etc. that all the tasks post this modified one were rescheduled automatically in time.
Hi,
When inside Gantt view please use cog wheel icon on top right and select ‘Enavle Auto Scheduling’. With this option on dragging a task forward will move all dependent tasks forward too.
Here you can read more about auto-adjustments in general – https://freedcamp.com/Freedcamp_LxR/Freedcamp_Devel_yOf/wiki/wiki_public/view/hJbab
Regards,
Igor